CERTIFER SA
18 RUE EDMOND MEMBREE
59308  Valenciennes
N°TVA : 73411047285
 

Customer: FAST Consortium
Place of execution: Saudi Arabia
Project duration : 2014 – 2019
Team: 1 project Manager and 8 Assessors

PROJECT’S DESCRIPTION:

The metro network of Riyad is composed of six separate lines.
The mission of CERTIFER covers the Lines 4, 5 and 6.
Each line is characterized as follow:

  •  Line 4 (Orange Line) reaches to King Khalid International Airport from King Abdullah Financial District (KAFD), mainly on a mix of elevated and at-grade alignment. The length of the line is around 29.6 km and it features 8 stations (3 common with Line 6), in addition to 1 transfer station with Lines 1 and 6.
  •   Line 5 (Yellow Line) runs underground in a bored tunnel along King Abdulaziz Street, between King Abdulaziz Historical Center and the Riyadh Airbase, before connecting with King Abdullah Road. The length of the line is about 12.9 km and it features 10 stations, in addition to 2 transfer stations with Lines 1 and 2.
  • Line 6 (Purple Line) follows a half-ring starting at King Abdullah Financial District, passing by Iman Mohamed Bin Saud University and ending at Prince Saad Ibn Abdulrahman Al Awal Road. It runs mostly elevated except along Sheikh Hasan Bin Husein Bin Ali Street. The length of the line is approximately 30 km and it features 8 stations (3 stations are common with Line 4), in addition to 3 transfer stations with Lines 1, 2 and 3.

The commercial speed shall be at least between 40 and 45 km/h.
The transportation system will include the rolling stock, a Urbalis 400 (an urban transport solutions of Alstom), control command and signaling system and platform screen doors.

Sind Sie von diesem Produkt interessiert? Lassen Sie uns ihre Personalien zurück, um durch unsere Dienste wieder Kontakt aufgenommen zu sein.

Name *

First name *

Company *

Postcode *

E-mail *

Tel *

* Erfüllen Sie alle obligatorischen Felder bitte

CERTIFER's missions

CERTIFER carried out an Independent Safety Assessment mission by ensuring that the safety objective of a the system is met at all times during its lifetime and by verifying compliance with regulations, standards and best practices of the system designed and implemented.
The mission covers the following aspects:

  • Rolling Stock;
  •  Tunnels and Stations;
  •  Power Supply;
  •  Control-Command & Signaling;
  •  SCADA;
  •  Platform Screen Doors;
  •  Interface Management;
  •  Safety Management;
  •  Risk Assessment;
  •  Operation ;
  •  Maintenance.
No additional info

You could also be interested in the following products :

Top
Dear users, this website stores cookies on your computer. Their purpose is to improve your website experience while providing you with more personalized services. Cookies are also used for ads personalisation.

If you would like more information about the cookies we use, please see our Privacy Policy. By accepting cookies, you consent to their use. You can also adjust their settings. If you refuse cookies, your information will not be tracked when you visit this site. Only one cookie will be used in your browser to remember your preference not to be tracked.
Alle ablehnen
Change the parameters
Accept all cookies
Cookie-Einstellungen bearbeiten